Post
Oxygen Not Included: Salt Water Geyser Utilization Build Guide
Explains how to obtain water using a saltwater geyser, produce bleach stone through geotuning, and build an efficient power generation system using steam turbines.
1. 💧 Early Saltwater Geyser Usage: Simple Water Purification System
- ✅ In the early stages, use a slime algae pump to pump up saltwater and purify it for use.
- ✅ Use a liquid pressure sensor to stop the pump when it exceeds 10kg.
- ✅ Use slime algae material for the pipes, but they are vulnerable to high temperatures, so they need to be cooled by spraying water.
00:02 - 00:53
1. 💧 Early Saltwater Geyser Usage: Simple Water Purification System
- ✅ In the early stages, use a slime algae pump to pump up saltwater and purify it for use.
- ✅ Use a liquid pressure sensor to stop the pump when it exceeds 10kg.
- ✅ Use slime algae material for the pipes, but they are vulnerable to high temperatures, so they need to be cooled by spraying water.
00:54 - 01:37
2. ⚙️ Bleach Stone Production Strategy Through Geotuning
- ✅ Geotuning a saltwater geyser allows you to obtain bleach stone, and the amount of bleach stone produced is greater than the tuning cost, making it virtually sustainable indefinitely.
01:38 - 04:41
3. ⚡ Building a Power Generation System Based on a Geotuned Saltwater Geyser
- ✅ Install auto-sweepers and conveyor loaders made of steel.
- ✅ Secure an internal space of 20 tiles and install 4 steam turbines.
- ✅ Install thermo-aquatuners and temperature sensors to build an automated system.
- ✅ Liquid vents put the turbine discharge back into the steam room.
- ✅ Install cooling pipes in the thermo-aquatuner.
- ✅ Sprinkle a small amount of crude oil where the geyser and thermo-aquatuner are located.
- ✅ Install conductive wires and conveyor rails.
- ✅ Install transformers above the steam turbines to manage power supply.
| 설비 | 재질 |
|---|---|
| 자동 정리기, 컨베이어 적재기 | 강철 |
| 센서 | 설정값 |
|---|---|
| 온도 센서 | 150도 미만 |
| 파이프 온도 센서 | 20도 초과 |
04:42 - 05:02
4. 🔄 System Maintenance and Management Tips
- ✅ If the pipes stop, develop a submerged or oil well to supply water.
- ✅ If the pipes are full, you can collect the steam in the tiles.
05:03 - 05:34
5. ♨️ Additional Settings for Maximizing Geotuning
- ✅ Install an auto-sweeper to remove salt and set a timer to increase efficiency.
- ✅ Install 5 geotuners on the base and tune the saltwater geyser.
- ✅ The temperature rise and eruption volume increase depending on the number of tunings.
05:35 - 06:48
6. 💨 Operating Principle and Efficiency of the Completed System
- ✅ High-temperature saltwater evaporates from the geotuned geyser, producing electricity through steam turbines.
- ✅ The reason for laying crude oil is because steam continues to accumulate.
- ✅ You can use the turbines to drain water whenever there is a shortage.
- ✅ Cool the heat of the steam turbines to maintain efficiency.
- ✅ Divide the steam room and manage it with low and high temperatures.
06:49 - 07:47
7. ⚙️ Auto-Sweeper and Bleach Stone Processing Utilization
- ✅ Set a timer on the auto-sweeper to efficiently remove salt.
- ✅ Process the removed salt into bleach stone using a bleach stone pulverizer.
- ✅ The completed system provides excellent performance, enough to run multiple water electrolyzers.
- ✅ It is best to build from the saltwater vent first after the exosuit is completed.